20 Dec, 2019

McColl: Ferries ‘should be scrapped’

Makes Statement0 Comments

The former chairman of Ferguson Marine says he is taking legal advice on whether the Scottish Government’s report on his management, drawn up after it took ownership of the yard, was defamatory. He says the report is aa “snow job” to cover up the role of Caledonian Maritime Assets Limited, the government agency involved in procuring the ferries. McColl says design changes by CMAL caused the delays. and cost overruns.

[Criticism of the management team is] outrageous and unacceptable – the team selected were some of the best in the UK, and head and shoulders above those in there now. I’ve asked if we can sue them for defamation of character. There needs to be an inquiry. The way they’ve handled this is incompetent.

McColl also challenged the Scottish government’s plan to spend £100 million completeing the ferries, which would write off more than £80m already spent on them, as well as the £45m in loans from the Scottish government that have already been written off.

You’d be better building from scratch and to a design that’s more suited to what’s needed. They could probably build three smaller vessels for less than £100m and it would give them more flexibility.

31 Aug, 2019

Administrator: Buyers expressing interest in yard

Makes Statement0 Comments

Administrators for Ferguson’s say they have held talks with several potential buyers (the exact number is not known) and are “encouraged” by the interest so far. The yard will be bought by the Scottish government if a private buyer is not found within four weeks of the date of the firm going into administration. Deloitte:

The joint administrators are undertaking a sale process and are actively engaged in discussions with a number of potentially-interested parties, however it is early in the process and therefore it is not appropriate for us to comment further at this stage. We have been encouraged by the level of interest in the yard so far but would encourage any remaining parties who may have an interest to contact us.

The Scottish government:

Ministers remain committed to the completion of vessels, securing jobs, and working towards finding a solution to support future shipbuilding at the site. Deloitte, as administrator, is currently going through the process of market testing for a private buyer. We will also start work to determine the optimal structure for the yard to ensure its long-term future. Our first priority is to establish a new delivery programme to ensure the completion of the CMAL ferry contracts.

19 Aug, 2019

Mackay: Ferry delivery schedule must be set by October

Makes Statement0 Comments

Speaking after meeting board members at the shipyard, Mckay says the new delivery schedule for the two ferries must be set by October.

We have always been clear that we want to complete the vessels, secure jobs and give the yard a future. On Friday, I met with the excellent workforce and stressed the Scottish government’s commitment to achieving the best possible outcome for the yard. Today, I convened the first meeting of the newly-established programme review board and tasked them with establishing a new delivery schedule for both vessels and a revised cost window. This group will help assess the current situation and ensure the effective and efficient delivery schedule of the CMAL ferry contracts as quickly as possible.

15 Aug, 2018

Government confirms summer 2019 delivery

Makes Statement0 Comments

Gibson confirms the MV Glen Sannox will enter service in the summer of 2019:

Regarding deployment of the Glen Sannox on the Ardrossan route, it was confirmed to me on August 14 through a parliamentary question that it will enter service next summer, with a June delivery followed by two months of crew familiarisation and sea trials.