MV Glen Sannox

MV Glen Sannox27 posts

MV Glen Sannox and its sister ship, known as Hull 802, are passenger ferries, currently being built by Ferguson Marine in Port Glasgow, Scotland. The Glen Sannox, which is to serve the Arran route, was originally scheduled to go into service in 2018. Production delays have led to significant cost overruns.

Latest News view > Click for Biography view
3 Apr, 2022

Ferry engine fears

Interview0 Comments

Concerns are growing about engines purchased for the two Calmac ferries more than five years ago. Despite costing four million pounds, the state run Ferguson shipyard has never tested them. The process of testing allows ships engines to be both assessed and prevented from losing condition. It has been revealed that the first time this will be done is late summer 2022 which may be too late and they may seize up. Dr Spyros Hirdaris a head of Maritime Safety:

There is a high possibility that the ferry engines won’t work and it seems very high risk to expect everything will go according to plan. If you have a car for a long time and never switch on the engine it’s probably not going to work. It’s extremely important the engines are tested on board so it’s not a good thing that they haven’t been tested for all this time. They should have tested the functionality of the engines. There could be problems because the engines have been there for a long time. The engines could halt, there could be malfunctions in some of the sub-systems, there could be problems with lubrication and corrosion of engine components.There are a number of things that may not work, for example the dual-fuel system may not operate properly because it’s such a long time since it has been tested.

15 Mar, 2022

Anger at Scottish Government over Calmac ferry secrecy

Makes Statement0 Comments

In the Scottish Parliament, Shadow Transport MSP Graham Simpson expresses his frustration at the lack of answers over how much longer it will take to get the Scottish ferries ready.

 Well, I’m asking a question in this chamber, and I expect to get an answer and the minister has not made an attempt to answer the question, which is by how long the ferries are delayed. It is not acceptable. We’re at a crisis point here. Just yesterday, only 13 out of CalMac’s 29 routes were operating normally. Islanders are at their wits’ end. There’s no slack in the system, so when a ferry breaks down, the knock on effects are horrendous. We need a steady pipeline of new ferries being ordered.

Business Minister Ivan McKee responds:

The Scottish Government is committed to ensuring that Scotland’s islands have got the connectivity. That’s why we are making that substantial investment into ensuring that that is indeed the case. The details of the impact of that cable issue are being worked through at the moment and we will report back when the robust information is available as to the implications in terms of time and cost of that particular issue.

The Turkey order had been part of a £580 million investment in further expanding the ferry service. In contrast McKee’s predecessor, Graham Dey had asked for £1.5 billion over 10 years. A cross party visit to the shipyard planned for January had been cancelled and rescheduled for April 2022 . A freedom of information request to get an answer for when the two ferries will be ready, failed to be answered within the required 20 days and has been escalated to an appeal.

2 Mar, 2022

Ferries three years overdue, £110m cost overrun predicted

Production delay0 Comments

The ferries are now three years overdue, less than half built and are predicted to cost £110 million more than originally estimated. Hair says that the ships are “significantly less than half built” and that 95% of the ships design has not been agreed with CMAL more than four years after the ships were ordered. He said that more naval architects and engineers have been taken on to deal with this. The shipyards executive said that the planning process for changes to the design under the yards prior to nationalisation was “either absent or badly flawed”:

The number of £110m [the extra money needed to finish the project] has been arrived at from a very detailed examination of the two vessels and an understanding of the work that needs to be done in order to bring them up to a viable standard.It is a very significant number but it is a number that has been based on as rigorous an assessment as we’ve been able to carry out. It’s one where I am confident we can deliver the two vessels for that amount.

Committee member and Tory MSP Peter Chapman said people would find the situation “absolutely incredible”.

How the heck do you get to £110m, which is more than what the original cost was to start from scratch with a pile of steel and nothing?

10 Feb, 2022

Short cable replacement delays ferries

Production delay0 Comments

In a letter to Lockhart, convenor the Scottish Government’s Net Zero committee, Ferguson Marine’s turnaround director says that in the week before Christmas 2021, engineers unwound coils that had been installed in late 2018/early 2019 and found some of them were too short to reach the necessary equipment. After three weeks of investigation, Ferguson engineers believe that at least 400 cables will need to be addressed, with the worst case requiring 939 cables to be replaced. The faulty cables were installed by a sub-contractor before the shipyard went into administration – none of the cables were installed after the Scottish Government took control of the yard. Most or all the vables will need to be cut out and the process started again. Hair says it is not currently possible to determine the impact on schedule and cost of the problem. Hair:

I regret to advise you that a problem has recently emerged with the build of 801 which I thought I should immediately bring to your attention. Commissioning and further cable installation cannot take place until the legacy cables are corrected, delaying the overall project to deliver 801. There will inevitably be knock-on effects that will delay the schedule for 802. At present it is not possible to determine the impact on schedule and cost.

28 Jan, 2022

HCC wins £5m insurance judgement against CMAL

Judgement0 Comments

A summary judgment is granted in favour of HCC International insurance aganst CMAL to claim £5 million owed as a result of the way ministers bought the shipyard when it was in administration. The Scottish government, which owns CMAL, said it was aware.  Deputy High Court Judge Simon Gleeson:

It is easy to see why this decision seems to have caused so much anger and irritation amongst the Scottish ministers. In paying for the business of FMEL (Ferguson Marine) by reducing FMEL’s liabilities to them, they believed that they were simply transferring their own money from one pocket to another, with the transaction having no impact on their overall obligations. The discovery that the choice of transaction structure had resulted in their being required to pay a little over £5million to a third party must have been highly unwelcome.

Scottish government spokesman:

We are aware of a summary judgment that has been made in the English courts in relation to the claim.

22 Jan, 2022

Ferry Action Group raises design concerns

Design Change0 Comments

The Arran Ferry Action Group raises concerns about the absence of a key hull feature required for the Glen Sannox to operate efficiently at 14.5 knots. Additional confusion arises over the divergence of design between Glen Sannox and sister ship Hull 802, which were intended to be identical in design and specification. Chairman Sam Bourne:

It is such a terrible mess. The whole thing is complete confusion and it affects the performance of the boats. Fitting a ducktail now is bound to further delay the completion of the vessel. And if it is needed on 802 why is it not on Glen Sannox which has the same hull. You are going to have two boats that do not meet the spec that was given and are not identical. If one has it and the other hasn’t it just won’t meet the performance targets set. If the boats don’t meet the performance specifications, CMAL can refuse it and then who owns these vessels. If you have an inefficient hull form, they will cost more money to operate, and the green criteria they try to hit, you can throw those in the bin. Serious questions have to be asked of those who run the businesses at the time to allow this.

CMAL:

We are satisfied that the vessels meet the required specification, and are continuing to work closely with Transport Scotland, Scottish Government and Fergusons to manage the delivery of the two vessels.

19 Jan, 2022

Chairman and board member step down

Board Change0 Comments

Chairman Alistair Mackenzie and board member John Hudson both step down from their roles at Ferguson marine for personal reasons. Mackenzie:

I have decided for personal reasons that now is the right time to stand down. I have been proud to serve on the board of Ferguson Marine, supporting the business during a highly challenging period as it recovered from administration and through a transformation programme. Working with the wider board and senior management team, significant progress has been made to improve governance, processes and systems and to strengthen the workforce.

I would like to thank John Hudson as he departs, as well as the wider board and shipyard workforce, for their commitment and support during the last 18 months. With the arrival of a new chief executive, and three new board members in the coming months, I am sure the shipyard will continue to strengthen.

16 Dec, 2021

Ferguson’s: Hair to step down

Makes Statement0 Comments

Ferguson’s announces, that after two years at the company, Hair will step down as turnaround director. He spent two years as turnaround director. He will be replaced by Tydeman in February. Chairman Alistair Mackenzie:

[It is] the right time to welcome a permanent and longer-term leader…The board and wider team at Ferguson Marine extend our thanks to Tim Hair for his leadership, expertise and commitment over the past two years. It has been challenging, not least because of a global pandemic, but he has implemented a series of important changes, systems and controls and built an experienced and skilled team to strengthen the business and establish a solid footing for growth.

24 Jun, 2021

Delivery date slips by 15 weeks

Production delay0 Comments

Ferguson Marine says the Glen Sannox will now be handed over between July and September 2022 – 15 weeks later than expected. The ship, destined for the Arran route, was originally due to enter service in 2018/19. The nationalised shipyard says Covid disruption and a shortage of local skilled labour were to blame. The comapny says it said it had only been able to recruit 40 skilled workers locally, 100 short of its target – and was now having to recruit overseas workers, via sub-contractors. The second ship, currently known as Hull 802, will be delivered between April and July 2023, according to the latest schedule. Turnaround director, Tim Hair:

I know the further delay to the project will be a disappointment to island communities and others who await the arrival of the new ferries. There remains a lot of work to do on the vessels, but it is important to recognise the level of progress too, as well as the significant operational improvements we have implemented to introduce robust and effective business processes. We have, in effect, created a functioning shipyard business from a standing start.

11 Mar, 2021

Pandemic shutdowns add £4.3 million costs

Makes Statement0 Comments

An extra £4.3m in costs have been added to the cost of the MV Glen Sannox and it sister ship. The Port Glasgow shipyard had to suspend working for four months during the first lockdown and was closed for another four weeks earlier this year. The shutdowns cost £3.3m and £1m respectively.

Tunaround director, Tim Hair, says the Covid shutdowns were being treated as “exceptional costs”, but the previously-announced remedial work, costing £110m-£114m, remained within budget. Hair said that 80% of design work was now signed-off by regulators and that the latest delivery schedule of April to June 2022 for Glen Sannox, and December 2022 to February 2023 for the second ship, was still achievable. Hair says the yard should be able to take on new work from next spring.

To date, 191 applications have been received for skilled workers, with 40 so far identified as having the relevant skills.

25 Feb, 2021

Shipyard to recruit 120 extra workers

Hire0 Comments

Ferguson Marine announces it is hiring 120 extra staff, mostly pipe fitters and steel workers. The extra workers will mean the shipyard can be in production seven days a week during spring and summer and will bring total number of staff to more than 500. The new workers will be working on MV Glen Sannox and hull 802 for at least six months. Turnaround Director Hair:

Last year was challenging, with disruption created by the pandemic, but we’re confident we can increase momentum in 2021. We are confident, despite many challenges, 2021 will be a pivotal year in securing the long-term future of the shipyard. We must do everything possible to deliver the dual fuel ferry programme, improve productivity, secure contracts for future vessels, and protect local jobs.

9 Dec, 2020

Holyrood committee report published

Financial Report0 Comments

Holyrood’s Rural Economy and Connectivity Committee publishes a report calling for “root and branch” reform of the system for procuring ferries and concluding that the established procedures are “no longer fit for purpose”. Former bosses at Ferguson shipyard, ministers, state-owned CMAL and Transport Scotland are all criticised. Committee convener Edward Mountain:

All parties involved must share in the responsibility for the catastrophic failure to deliver this contract on time or on budget. A lack of due diligence, poor project management and a failure by all parties to take the necessary action to resolve problems as they emerged means that the cost of the contract has increased from £97m to almost £200m while the island communities who are relying on theses ferries to be delivered continue to suffer.

Goverment spokesperson:

We remain fully supportive of the efforts of CalMac, CMAL and Transport Scotland in delivering ferry services on the Clyde and Hebrides Network and to the Northern Isles, but we also recognise the challenges in doing so and the need for continuous improvement to optimise delivery. We have already committed to commission a study of the legal structures and governance arrangements which exist between the “tripartite group” of Transport Scotland, CMAL and CalMac and will publish a ferries stakeholder engagement strategy.

CMAL:

We have a successful track record of delivering ferry projects on time and budget and we are committed to continuous improvement of our processes, so steps are already being taken to further develop the planning process for new ferries.

9 Sep, 2020

Dry dock repair works completed

Announcement0 Comments

The ferry returns to the water after dry dock works are completed. 42 tonnes of mussels were removed from the hull, its bulbous bow replaced, paint repaired, and external welding completed. Hair:

Following a period of uncertainty due to COVID-19, it has been really gratifying to see our team return to outdoor working on MV Glen Sannox. We’ve made some solid strides forward over the last few weeks on MV Glen Sannox and have slightly extended the dry dock period to take advantage of the stability of the vessel whilst stationed there to carry out some additional tasks. Now that the ferry has been brought up to its current condition and has returned to our shipyard, the next steps will include work on the superstructure, electrical work and the installation of approximately 16km of pipework.

11 Aug, 2020

Enters dry dock

Repair0 Comments

The Glen Sannox enters the Dale Marine dry dock, a short distance down thr river from Port Glasgow, for remedial work. The ship will have its bulbous bow replaced, paint will be repaired and marine growth will be removed. The ship is due to return to the Ferguson yard at the end of August. Turnaround director Hair:

This is a key milestone in the recovery programme for the dual fuel vessels. Some work has been carried out on MV Glen Sannox at the shipyard, but the dry dock period is important because it will bring the vessel up to a condition that will allow us to move forward in earnest with the vessel completion plan. It is also another clear sign of recovery for the shipyard business and comes only weeks after the launch of a steel barge for a customer in the offshore oil and marine sector.

20 Dec, 2019

McColl: Ferries ‘should be scrapped’

Makes Statement0 Comments

The former chairman of Ferguson Marine says he is taking legal advice on whether the Scottish Government’s report on his management, drawn up after it took ownership of the yard, was defamatory. He says the report is aa “snow job” to cover up the role of Caledonian Maritime Assets Limited, the government agency involved in procuring the ferries. McColl says design changes by CMAL caused the delays. and cost overruns.

[Criticism of the management team is] outrageous and unacceptable – the team selected were some of the best in the UK, and head and shoulders above those in there now. I’ve asked if we can sue them for defamation of character. There needs to be an inquiry. The way they’ve handled this is incompetent.

McColl also challenged the Scottish government’s plan to spend £100 million completeing the ferries, which would write off more than £80m already spent on them, as well as the £45m in loans from the Scottish government that have already been written off.

You’d be better building from scratch and to a design that’s more suited to what’s needed. They could probably build three smaller vessels for less than £100m and it would give them more flexibility.

25 Sep, 2019

Administrator lists debts: Taxpayer owed £50m

Makes Statement0 Comments

A “statement of affairs” produced by Deloitte, the administrator of the shipyard, show £49.7m is owed to the Scottish government – nearly £5m more than previously revealed. The Scottish government said it provided two commercial loans totalling £45m to Ferguson Marine, on which interest applies. The new figures also reveal that two partially-built CalMac ships at the centre of the firm’s collapse have been valued at £48.3m, nearly half the value of the £97m deal agreed to build the ships. Ferguson Marine went bust owning more than £73m. Further details from the document show that:

  • £15.8m is owed to finance firm HCCI
  • The Scottish government is owed £49.7m
  • A total of £3m is owed to Clyde Blowers Capital, owned by former Ferguson boss Jim McColl
  • There is an outstanding debt of £426,000 owed to HMRC
  • The 300-strong workforce is owed £164,000 in overtime, holiday pay and pension contributions
  • £1m is due to the European Commission.
  • £3.9m is owed to business creditors, including a number of local Inverclyde companies
7 Sep, 2019

Glen Sannox still without windows

Production delay0 Comments

It emerges that the bridge of the Glen Sannox still has no windows almost two years after launch. Black shapes were instead painted on the control room of the Glen Sannox prior to launch by Nicola Sturgeon in November 2017. GMB Scotland secretary Gary Smith:

[An inquiry] will also need to establish why a ferry ‘launched’ nearly two years ago has no windows on its bridge. What appears to be windows is actually black paint.

Unnamed source:

Fake windows were painted on a couple of years ago. It’s thought it was to make the boat look more finished than it really is.

31 Aug, 2019

Administrator: Buyers expressing interest in yard

Makes Statement0 Comments

Administrators for Ferguson’s say they have held talks with several potential buyers (the exact number is not known) and are “encouraged” by the interest so far. The yard will be bought by the Scottish government if a private buyer is not found within four weeks of the date of the firm going into administration. Deloitte:

The joint administrators are undertaking a sale process and are actively engaged in discussions with a number of potentially-interested parties, however it is early in the process and therefore it is not appropriate for us to comment further at this stage. We have been encouraged by the level of interest in the yard so far but would encourage any remaining parties who may have an interest to contact us.

The Scottish government:

Ministers remain committed to the completion of vessels, securing jobs, and working towards finding a solution to support future shipbuilding at the site. Deloitte, as administrator, is currently going through the process of market testing for a private buyer. We will also start work to determine the optimal structure for the yard to ensure its long-term future. Our first priority is to establish a new delivery programme to ensure the completion of the CMAL ferry contracts.